A long and productive day at the Electron Workshop
A long and productive day at the Electron Workshop – LVL Structural beams in place for the mezzanine / podcasting studio, and finally the enormous hole we jack hammered in the floor to level off for the floor was laid as a concrete slab. So far, all the work at the Workshop has been done […]
Progress at the Electron Workshop…
Progress at the Electron Workshop… Cutting out the slab in order to jack hammer – We’ll then apply a leveling compound. As the warehouse was originally an auto garage, the floor has both a work pit, and drainage areas – As an office, these features are not particularly useful… So level we must!
Photos by Aaron Tester
Photos by Aaron Tester
4000 PSI
We started out stripping the walls with a petrol powered 4000psi pressure washer – Slow, and wet. We switched to sandblasting…